| V
| Codename
| Development
| Finishing
| Qualification
| Release
| Stabilisation
|
| 1.10
| Gute Laune
| ??
| ??
| ??
| ??
| ??
|
| 1.9
| Killer Queen
| Weeks 30-05
| Week 06
| Weeks 07-10
| Sun 2009/03/07
| Weeks 11-12
|
| 1.8
| Breathless
| Weeks 09-25
| Week 26
| Weeks 27-28
| Sun 2009/07/12
| Weeks 29-30
|
| 1.7
| Firestarter
| To be scheduled
| To be scheduled
| To be scheduled
| 2008/12/7
| To be scheduled
|
| 1.6
| Summertime
| Weeks 08 to 16
| Week 17
| Weeks 18 & 19
| 2008/05/11
| Weeks 20 & 21
|
| 1.5
| Lothlorien (released)
| Weeks 46 (2007) to week 02 (2008)
| Week 03
| Weeks 04 & 05
| 2008/02/03
| Weeks 06 & 07
|
Phases details
- Development time frame is 8 weeks long
- Finishing phase contains:
- The new features profiling (done by devs, can be done with VisualVM profiler for ie)
- The new test cases creation in the Qualification page (currently done by devs, help is welcomed)
- Adding new features in the Features page
- Adding main changes in the New Features Highlights page
- The documentation updates (currently done by devs, doc writers are welcomed)
- The translations updates (done by translators)
- Qualification is planned to be done over only 2 weeks and is done through the Qualification page
- Stabilization is dedicated to bug fixing on recently released version.